Google will invest $17 billion in its first Wyoming data center, in Laramie County, the company announced on November 5. Reuters reported the same day that the announcement came "as political resistance to data center expansion grows following the US midterm elections."

The resistance has a number attached. Of 41 data center-related ballot measures voted on this week, all but one went against data centers, according to Ballotpedia figures cited by Reuters.

The Wyoming plan

The site would run on a planned 702-megawatt fuel-cell development with carbon capture and storage, with fuel cells supplied by Bloom Energy. Steve Walter, Google's vice president of global infrastructure and energy, wrote that the project is the largest planned development of its kind to date and brings Google's total contracted carbon capture capacity to nearly 1 gigawatt. Capture is described only as covering "a large majority" of emissions, with no percentage, completion date or cost split given. Reuters named Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital as partners.

Wyoming is a Republican stronghold where Donald Trump won more than 70% of the 2024 presidential vote, Reuters noted. Reuters did not say that is why Google chose it, and Google has not said so either.

The market reaction

Investors treated the week as a policy shock. Aiweekly, citing CNBC (the CNBC original could not be retrieved for this article), reported that the Nasdaq 100 fell 6.4% on Thursday, a record $2.3 trillion loss in market value, while the Philadelphia semiconductor index dropped 12%. Nvidia and Qualcomm each fell more than 9%. Aiweekly attributed the move to investors pricing in the threat of the election results to data center buildouts, which is that outlet's framing rather than a named analyst's. Reuters said wins by candidates opposed to data center expansion in key Texas and Georgia races added to the concern, and that Bloom Energy shares slumped more than 14%.

There was also a sign of caution from inside the industry. Reuters, citing Bloomberg, reported that Microsoft declined to expand a Texas data center deal with Nscale and planned tighter oversight of projects from Nebius, IREN and Nscale.

Lam Research, a chip equipment maker, took a different tack that evening: its board approved a $25 billion share buyback, according to a company release dated November 5.

Google's Wyoming site now serves as a test of whether on-site power and a friendlier state can sidestep local opposition. The next ballot results and permitting fights will show how far that works.

Sources: Reuters via Investing.com · Aiweekly, Wyoming data center · Aiweekly, Nasdaq rout · Lam Research release